1. BASIC ENGINEERING
a) Establish plot plan (Equipment Location)
b) Prepare engineering specifications
for all piping classes.
c) Establish piping class and valve type
requirements.
2. DETAIL ENGINEERING
a) Prepare pipe routing studies and pipe
planning studies.
b) Prepare design and detail drawings
on underground piping systems.
c) Prepare final design and detail drawings
and elevation drawings showing all
lines in sufficient
detail to permit the preparation of isometric drawings.
d) Prepare isometric drawings.
e) Prepare pipe support location drawings
and detail drawings.
f) Prepare bill of material sheets for
each line.
g) Prepare piping bulk material take-off
based on approved plot plan and
approved P & I
flow diagrams.
h) Prepare drawing for steam tracing.
i) Prepare line numbering schedule, piping
line list and data summary.